Hopper-bottom silo under assembly, jacked up on chain hoists fixed to the orange frames around the cell

Laon · France · 1,100 t · Silomasters

Hopper-bottom silo of 1,100 tonnes at Laon, France

We have started the assembly of a hopper-bottom silo of 1,100 tonnes at Laon, France: 10 metres across, 26.3 metres tall, Silomasters equipment.

Location
Laon, France
Capacity
1,100 t
Type of work
Silo mechanical assembly
Technology
Silomasters
Year
2026

Published 2 minutes read

Contents
  1. The numbers
  2. A tall, narrow silo
  3. How a silo grows: from the top down
  4. Beside a plant that keeps working
  5. What comes next

We have started the assembly of a hopper-bottom silo at Laon, in northern France. The equipment comes from Silomasters.

Hopper-bottom silo under assembly, jacked up on chain hoists fixed to the orange frames around the cell
The jacking frames and chain hoists, all the way round the cell. The roof is already finished; the body grows underneath it.

The numbers

ModelI1015-45
Capacity1,100 tonnes
Diameter10 metres
Overall height26.3 metres
Bottomhopper

A tall, narrow silo

26.3 metres at 10 metres diameter is a height-to-width ratio of more than two and a half. For a grain silo, that is a lot.

A short, wide silo forgives. A slender one does not: a few millimetres out at the base are amplified over the whole height, and by the top it is a problem that cannot be corrected any more — it has to be taken apart. Which is why verticality is checked on every ring, as the structure grows, not at the end.

The hopper bottom raises the structure as well. The cell does not sit on the raft; it sits on a support structure, and the cone discharges by gravity into whatever is underneath. You gain complete emptying, with no machine needed to clear the last of it off the floor — in exchange, everything that gets installed, gets installed up at height.

How a silo grows: from the top down

The photographs show the method, and it surprises anyone seeing it for the first time: you start with the roof.

The roof is assembled low down, close to the ground, on the first ring. Then the whole assembly is lifted on chain hoists fixed to the orange frames around the cell, and the next ring goes in underneath. Lower, bolt, lift again. The silo grows from the top down, ring by ring.

The roof of the hopper-bottom silo, with the handrail and the vent already fitted
The roof, with the handrail and the vent in place, before the cell starts to rise.

The advantage is that almost everything is done at low level: the roof joints, the handrail, the vents, the sheet of every ring. People climb only as far as they have to, and at 26 metres that counts — for safety and for speed alike.

The jacking frames are ours. They travel with the crew, from one site to the next.

Beside a plant that keeps working

The silo is going up between existing buildings, next to a cell already in service.

The site at Laon: the new silo under assembly, beside the existing plant
The site: little room, machines all around, and a plant that does not stop working.

That changes the organisation more than people expect. The crane cannot stand just anywhere, material cannot be unloaded where the truck arrives, and the programme fits the client's, not the other way round. Each ring reaches its position when it is needed, not a week early.

What comes next

We continue with the remaining rings, the cone and the support structure, then the connections to the existing flow and the tests.

We will come back with photographs as the silo rises.

See also grain silo mechanical assembly or anchoring steel grain silos.

More work

Similar projects

Mulmix pellet silo mounted on a raised concrete platform at the Biotim plant in Timișoara, with a telescopic crane on site

Timișoara, Timiș county · 2,000 t · Biomass and pellets

2,000-tonne pellet silos at Biotim Timișoara

We have started assembling the 2,000-tonne pellet silos, with Mulmix equipment, at the Biotim biomass plant in Timișoara. How a silo goes up, ring by ring.

Metal silo roof nearly complete, aeration system installed alongside — Rosilo

Schwedt · Germany · 4 × 11,000 t

Rosilo Starts Assembly of High-Capacity Metal Silos in Germany — 4 Cells of 11,000 Tons at Schwedt

Rosilo has launched a new high-capacity metal silo assembly project in Germany: at Schwedt, we are erecting four cells of 11,000 tons each — a total of…

mechanical assembly

Brăila · 36,000 t

The 36,000-ton Project in Brăila Nears Completion

We are nearing the final stage of installation for the 36,000-ton project in Brăila County, a large-scale agricultural facility that includes a complete…

Request a quote

A job like this one, at your site?

Tell us where the site is, what has to be done and the dates you are working to. We look at what the project needs, work out the resources and come back quickly with a clear proposal.

At home and abroad

Crews available for work in Romania and internationally.

A quick answer

We assess the timing, the people and how the job will be organised.

One person to talk to

From the first enquiry through to the end of the job.