Infrastructure works, foundations, silo fencing Crizbav (RO)

03 December 2018 – The weather allows the continuation of the works on the infrastructure of the concrete platforms and on the foundations of the hall and of…

Location
Crizbav, Brașov county, Romania
Type of work
Foundations and steelwork
Year
2018

Published

03 December 2018 – The weather allows the continuation of the works on the infrastructure of the concrete platforms and on the foundations of the hall and of the grain silos. We work with a team of 6 machines: 2 construction dump trucks, an excavator, a compactor, a backhoe and a bulldozer. The fencing of the grain storage base is almost completed, and the utilities: electricity and water supply are solved. In order to increase the safety of the equipment that will be supplied to the site, the perimeter lighting system and the video surveillance system are being worked on.

The completion of the isolated foundations of the FNC hall by the end of 2018 would represent a great achievement in the context of unfavorable weather and the approach of the winter holidays.  

More work

Similar projects

technology line

Timișoara, Timiș county · Biomass and pellets

Rosilo Begins Mechanical Assembly at Biotim Timișoara — Romania’s Largest Biomass Pellet Plant

The Rosilo team has officially started mechanical assembly works at the Biotim site in Timișoara, a landmark project for the Romanian bioenergy industry.…

mechanical assembly

Brăila · 36,000 t

The 36,000-ton Project in Brăila Nears Completion

We are nearing the final stage of installation for the 36,000-ton project in Brăila County, a large-scale agricultural facility that includes a complete…

Seed Treatment Station

Popești-Leordeni, Ilfov county

Grain Storage and Seed Treatment Plant – Popesti-Leordeni Project

Near completion: 4 buffer cells, fully mechanized grain flow with cleaner, and a seed treatment station installed inside the main hall. Table of Contents…

Request a quote

A job like this one, at your site?

Tell us where the site is, what has to be done and the dates you are working to. We look at what the project needs, work out the resources and come back quickly with a clear proposal.

At home and abroad

Crews available for work in Romania and internationally.

A quick answer

We assess the timing, the people and how the job will be organised.

One person to talk to

From the first enquiry through to the end of the job.